Scope/Solutions

Looking to reinvent the campus, Harvard Kennedy School (HKS) completed a major project in 2017 to add three new buildings linking the existing structures. During the first winter after the additions were put into service, snow accumulated on horizontal metal shelves and subsequently slid off onto the walkways below. SGH helped HKS by evaluating the existing buildings’ conditions and designing a retrofit to prevent snow and ice from sliding off.

Without available industry guidance for snow retention designs, SGH developed a plan to test the performance of several snow retention options to find the best solution for the school, given the variability of weather conditions and building elements. Highlights of our work included:

  • Reviewing the buildings’ design and identifying existing conditions leading to the accumulation of snow and ice
  • Evaluated three mockups during the 2019 winter season
  • Developed design documents for the retrofit
  • Assisted HKS during the bid phase by providing a list of bidders, leading a pre-bid meeting, issuing meeting minutes and addenda, answering bidders’ questions, reviewing bids, and recommending a firm to execute the work
  • Worked with HKS to develop phasing plans and review value engineering options
  • Provided construction administration services, including reviewing contractor submittals to compare with the design intent, periodically visiting the site to observe installation of the snow guard system, and helping the contractor address field conditions

Project Summary

Icon: completion-date

2017

Completion Date
Icon: construction-value

25k

Construction Value
Client(s)
Harvard Kennedy School
Specialized Capabilities
Facades & Glazing

Key team members

Christopher Grey
Principal

Additional Projects

Northeast

225 Binney Street

SGH provided building enclosure consulting services for renovating two historic, brick masonry buildings and constructing a new, six-story office building with below-grade parking at 225 Binney Street.
Explore
Northeast

Massachusetts Water Resource Authority, Beacon Street Line

Constructed in the 1870s, the Beacon Street Line carries water under the MBTA Green Line tracks in the busy Brookline neighborhood. SGH evaluated the pipe to determine if workers could safely enter, designed the repair, and provided engineering support during construction.
Explore