Boston, MA
Boston University, Tsai Performance Center
Scope/Solutions
The Tsai Performance Center hosts concerts, theatrical and dance presentations, lectures, film programs, and conferences. Boston University wanted to upgrade an outdated sound system with new audio and network components. The upgrade involved suspending three new speaker arrays, each weighing more than 1,200 lbs, from portions of the existing building structure. SGH analyzed the existing roof and proscenium framing for the new speaker loads, designed structural improvements to the framing, and provided structural construction administration services for the new speaker installation.
SGH worked closely with the owner, acoustic consultant, contractor, and rigging vendor to provide the following services:
- Investigated and documented existing conditions of the steel-framed roof and proscenium structures
- Analyzed the existing roof and proscenium structures for new speaker loads, including dynamic effects caused by the motorized rigging equipment, and prepared a summary report
- Coordinated with the rigging vendor to select rigging and suspension hardware
- Designed structural modifications to strengthen a portion of the existing proscenium structure
- Prepared structural drawings identifying rigging attachment locations on the existing structure
- Assisted the contractor to address issues that arose during speaker and rigging installation
Project Summary
Solutions
Repair & Rehabilitation
Services
Structures
Markets
Culture & Entertainment | Education
Client(s)
Communications Design Associates, Inc.
Specialized Capabilities
Repair & Strengthening
Key team members
Additional Projects
Northeast
Cultural Education Center and Grand Stair at Empire State Plaza
SGH evaluated long-term water leaks under the staircase and designed repairs. Following our work at the plaza, SGH investigated bowing of the marble wall panels and issues related to anchorage of the panels at the Cultural Education Center.
Northeast
Harvard University, Fogg Museum, Werner Otto Hall Addition
Soon after construction, occupants observed leakage through the plaza deck into the art storage room below and other issues outside of climate controlled areas with elevated humidity levels, including wet stains on the limestone facade.