Cambridge, MA

One Cambridge Place

Scope/Solutions

The headquarters offices of Camp Dresser & McKee occupied two office buildings in Kendall Square. CDM wanted to consolidate offices into a single structure. The developer required the new building within seventeen months in order to fit into CDM’s move plan. The project, which would provide CDM with parking for 235 cars and 160,000 sq ft of office space, needed a compressed design and construction schedule. SGH designed the new nine-story structure in time to obtain building permit sixty days after the initiation of design.

SGH designed a steel braced frame and composite steel beam superstructure with concrete slabs on composite metal deck. Highlights of our work on this project include the following:

  • Produced parking layout designs to accommodate public relations and permitting issues
  • Issued an early foundation design package to gain time in the architect’s schedule
  • Prepared steel reinforcement shop drawings for the foundation and the first floor slab, cutting approximately six weeks from the schedule
  • Developed waterproofing details
  • Designed blind side waterproofing due to the proximity of the new building to an existing nine-story building on the east side of the site

Project Summary

Icon: completion-date

2000

Completion Date
Solutions
New Construction
Services
Building Enclosures | Structures
Markets
Commercial
Client(s)
The Bulfinch Companies, Inc.
Specialized Capabilities
Building Design | Roofing & Waterproofing

Key team members

Pedro Sifre
Senior Principal
Paul Kelley
Consulting Principal

Additional Projects

Northeast

Watermark Kendall East at 250 Kendall Street

Watermark Kendall East brings an additional 144 apartments to a new residential complex, which also includes a 321-unit tower and parking structure constructed in an earlier phase. SGH consulted on the building enclosure.
Explore
Northeast

Hotel

Designed by Strickland and Blodgett in 1927, the hotel was constructed with a steel-framed structure clad with brick masonry and accented with decorative cast stone and limestone features. SGH investigated the causes of facade deterioration.
Explore